The building control approval for the Hinkley Point C nuclear site and the ancillary workers campuses and enabling work is being carried out by a private Corporate Approved Inspector, Regional Building Control Ltd.
Their appointment by edf (NNB) covers all the buildings which are not directly either regulated by the Office of Nuclear Regulation or are exempt buildings.
RBC have previously worked with edf on the construction of their nuclear training facility at Cannington Court, near Bridgewater.
The ancillary campuses and the park and ride facilities will provide accommodation and facilities for the construction workers for the main power station.
RBC Managing Director, Colin Jackson explained that being engaged in the construction of a major nuclear power station is a first for a private Building Control body and is a reflection of our expertise, professionalism and management skills. We are immensely proud to be a part of this project.